From one year ago-
Snowy 2.0
"The nation-building vision was for a big battery to be added to the Snowy Mountains Hydro-Electric Scheme. It was to be completed in four years (that is, by last year) at a cost of $2 billion without any taxpayer subsidy, bring down electricity prices, generate renewable energy and incur minimal environmental impact on Kosciuszko National Park.
Inspiring stuff. But not one of these grand claims has turned out to be true. Worse, Australian taxpayers and NSW electricity consumers will be up for billions of dollars in subsidies and increased electricity costs, all while Kosciuszko is trashed. Let’s have a quick recap.
Snowy Hydro
now expects completion in 10 years, not four,* by 2026. Some experts consider even this extended timeframe to be optimistic. Construction of the tunnels is running at least six months behind the latest schedule and the transmission connection is unlikely to be built by 2026 anyway. The all-up cost has increased at least five-fold, to $10 billion-plus, as energy experts warned the Prime Minister and the then NSW premier in 2020.
The underground power station and tunnels alone will cost more than $6 billion, and Snowy Hydro avoids mentioning the transmission connections to Sydney – $4 billion-plus for HumeLink and the Sydney ring – and to Victoria. To make matters worse, Snowy Hydro refuses to contribute to these transmission works, leaving it to electricity consumers to pick up the tab. Transmission tariffs in NSW will increase by more than 50 per cent if the NSW government allows Snowy Hydro to get its way, based on analysis in a Victoria
It’s been around for decades but pumped hydro power is gaining attention as a potential back up for renewable energy, which is increasing its share of the electricity grid. It’s also technology the federal government is interested in.
Despite the assurance that taxpayer subsidies were not required, the federal government was forced to shore up Snowy 2.0’s business case with a $1.4bn “equity injection”. Further taxpayer funding is inevitable, warned Standard & Poors when it downgraded Snowy Hydro’s credit rating in 2020.
Far from bringing electricity prices down, Snowy Hydro’s own modelling predicts that prices will rise because of Snowy 2.0.
As far as the claim that Snowy 2.0 will add 2000 megawatts of renewable energy to the National Electricity Market, Snowy 2.0 is not a conventional hydro station generating renewable energy. It is no different to any other battery, and as such it will be a net load on the NEM.
For every 100 units of electricity purchased from the NEM to pump water uphill, only 75 units are returned when the water flows back down through the turbine generators. Not only is the electricity generated not renewable, Snowy 2.0 will be the most inefficient battery on the NEM, losing 25 per cent of energy cycled.
And on the final claim of minimal environmental impact to Kosciuszko National Park, vast areas have already been cleared, blasted, reshaped and compacted. Hundreds of kilometres of roads and tracks are being constructed, twenty million tonnes of excavated spoil will be dumped (astoundingly, mainly in Snowy Hydro’s reservoirs), and noxious fish will be transferred throughout the Snowy Mountains and the headwaters of the Murrumbidgee, Murray and Snowy Rivers, devastating native fish and trout. The NSW government has even agreed to issue exemptions to its own legislation to override the prohibition of such pest fish transfers – an astonishing precedent.
The massive cost and environmental impacts of Snowy 2.0 cannot be justified for providing occasional longer-term storage."
https://www.smh.com.au/national/five-years-on-snowy-2-0-emerges-as-a-10-billion-...Updated - "Snowy Hydro has advised that its troubled Snowy 2.0 pumped hydro storage project in NSW will overrun its already-revised $5.9 billion budget and may not be fully online until the end of the decade.
The latest delay, of as much as two years, looks set to intensify worries about the reliability of the east coast electricity grid as owners of coal power stations accelerate closure plans.
The federal government-owned company said it is working to “reset” the timetable and budget for the project with key contractor Future Generation Joint Venture, controlled by Italy’s Webuild....
One of the huge tunnel boring machines used at the project, a 2000-tonne machine named Florence, has been essentially stuck for months in soft ground, while a “depression” has appeared on the surface, 30 metres above where it is located. Work is under way to stabilise the ground to allow the machine to resume tunnelling."
https://www.afr.com/companies/energy/snowy-2-0-faces-further-cost-increases-dela... (paywalled)